Here’s Why Construction Has Stopped For The William F. Evans Memorial Bridge In North Adams
Many North Adams residents who travel on the west end of the city have expressed frustration with the half-finished William F. Evans Memorial Bridge, which crosses the Hoosac River near West Package & Variety Stores on State Road.
Trust me, those narrow lanes can be sketchy if you're new to the area. I'm so used to them by now that they don't bother me anymore, and I drive over them every day. But this raises the question: why is the bridge construction taking longer than expected? Let's find out.

The Bridge Is A State-Funded Project, Not The City's
Because the bridge is part of state highway route 2, it is a project run by MassDOT, not the city of North Adams, as many have rumored. Funding comes the Bipartisan Infrastructure Program. The complete replacement of the bridge began in 2023, according to MassDOT’s website. However, construction is currently paused due to groundwater issues.

Read More: The Oldest Road In Massachusetts Has A Royal History

The Types Of Groundwater Issues Found Under The Bridge
The Berkshire Eagle reports that MassDOT informed them via email that during the removal of sections of the old bridge, workers found discolored soil and groundwater, which had a strong smell. Testing revealed the presence of Volatile Organic Compounds, chemicals that can vaporize from liquids or solids, as explained by the EPA.
The good news is that once the area is dry and no longer contaminated, construction of the bridge will resume later this month, with an estimated total cost of over $15 million. I don't know about you, but I'm certainly ready to have a nice wide bridge again.
20 Massachusetts Places That Will Make You Think You're in Another Country
Gallery Credit: Nancy Hall
Here's a List of All the Snakes Native to Massachusetts (Two Can Kill You)
Gallery Credit: Kate Robinson
More From WNAW AM